New Bridgewater Bridge – Tasmania

Tasmania’s largest-ever transport infrastructure project – the New Bridgewater Bridge, a 1.28 km, four-lane crossing of the River Derwent that replaces the 1946 steel-truss lift bridge.

Designed to improve safety and reliability for everyone who uses it, the bridge includes a shared walking and cycling path and strengthens the connection between Hobart’s northern suburbs and the Midland Highway.

As lead geotechnical designer, we delivered a foundation solution that helps the bridge perform in a challenging river environment – addressing highly variable ground conditions, seismic hazards, and flood-scour risk.

Awards

  • 2025–2026 Consult Australia Award for Innovation for Excellence

Services

  • Geotechnical investigation
  • Foundation design
  • Seismic geotechnics
  • Numerical modelling
  • Construction support
  • Verification testing

Client

  • McConnell Dowell

Year

  • 2022-2025
New Bridgewater Bridge – Tasmania

Project highlights

  1. Large-diameter monopiles to 91.5 m depth (believed to be the deepest of their kind in the Southern Hemisphere)
  2. One-borehole-per-pile investigation approach
  3. O-Cell load testing to verify performance and protect programme certainty
  4. 46/46 production piles achieved “Class 1” integrity in CSL testing

The challenge

Building a major bridge over a dynamic river system requires confidence in what lies below the surface and a foundation design that can cope with uncertainty. For the New Bridgewater Bridge, the geotechnical challenge included:
  1. Highly variable ground conditions beneath a river environment
  2. Seismic hazards (including liquefaction-related ground deformation)
  3. Flood scour risk (riverbed erosion during major flows)
  4. A need to confirm performance early to avoid redesign, delays and cost escalation during construction
Our goal was to help the project team make informed decisions and deliver a foundation system that was safe, resilient, buildable, and verified.
Tasmania’s largest-ever transport infrastructure project – the New Bridgewater Bridge

What we did

Tonkin + Taylor served as the lead geotechnical designer, working alongside the wider project team to design and validate a technically demanding bridge foundation solution. We combined detailed site investigations, advanced ground modelling, innovative interpretation methods, and verification testing to support a “right-first-time” installation approach, reducing rework risk and protecting programme delivery.

Deep monopile foundation design

We pioneered the design of large-diameter monopiles reaching depths of up to 91.5 metres, engineered for performance under variable soil and rock profiles, earthquake loading and potential ground deformation, and scour and river-driven loading conditions.

Targeted investigation – one borehole per pile: To reduce uncertainty and strengthen design confidence, our approach included one-borehole-per-pile site investigations—providing high-resolution ground information for each foundation location.

3D geological modelling to manage complexity: We developed detailed 3D geological models using Leapfrog, enabling a clearer understanding of subsurface variability and helping the team align design decisions with real ground conditions.

New ground classification and advanced interpretation: We developed new classification methods for the Tertiary Sedimentary Breccia and applied innovative analytical processes to better assess mixed soil-and-rock strength and stiffness—critical for predicting pile behaviour and designing efficiently.

More realistic numerical simulation of pile behaviour: We also developed a new numerical simulation process to evaluate pile behaviour under multiple loading conditions, improving realism and supporting confident decisions in a complex foundation environment.

Tasmania’s largest-ever transport infrastructure project – the New Bridgewater Bridge

Verification testing that protected time + cost

A major breakthrough on the project was the use of O-Cell load testing on four sacrificial piles to verify the design performance of large-diameter production piles. This testing confirmed that pile capacities exceeded the minimum requirements, preventing the need for redesign or lengthening during construction and avoiding potential delays and cost escalation. To confirm build quality, all 46 production piles achieved “Class 1” integrity in Cross-Hole Sonic Logging (CSL) testing, supporting a true right-first-time installation and reducing the need for remedial work.

Outcomes + benefits

Our work helped the project team deliver a foundation system designed and verified for long-term performance in a challenging river environment.

Key outcomes included:

  1. Reduced uncertainty through targeted investigations and 3D ground modelling
  2. Verified foundation performance through O-Cell testing, supporting programme and budget certainty
  3. High-quality construction outcomes, with 46/46 piles achieving Class 1 integrity
  4. A solution designed for seismic resilience and scour-related risk in the River Derwent
  5. A comprehensive dataset that provides a valuable reference for future projects in similar river conditions

Tasmania’s largest-ever transport infrastructure project – the New Bridgewater Bridge

Setting new benchmarks for geotechnical engineering

The New Bridgewater Bridge has set new benchmarks for geotechnical design and verification in complex river environments. The depth of the monopiles, the investigation strategy, and the testing-led validation approach have helped establish a stronger evidence base for bridge foundation design, supporting designers and asset owners on future projects worldwide.

Innovation for Excellence Award: What this recognition means

Tonkin + Taylor’s contribution to the project was recognised with the 2025–2026 Consult Australia Award for Innovation for Excellence, reflecting the value of combining innovation, engineering rigour, and collaborative delivery to achieve better outcomes.

“This achievement reflects what can be done when innovation, engineering excellence, and collaboration come together. The New Bridgewater Bridge shows that world-class engineering can deliver safer, greener, and smarter infrastructure.” Tim Fisher, Group Managing Director, Tonkin + Taylor

The project’s success establishes a lasting legacy, a proven model for delivering infrastructure that is cheaper, faster, more resilient and more reliable. The New Bridgewater Bridge stands as both Tasmania’s largest infrastructure investment and a landmark of Australian engineering excellence.

Tasmania’s largest-ever transport infrastructure project – the New Bridgewater Bridge

 

Explore geotechnical engineering (NZ)

Explore geotechnical engineering (AU)

Explore More Projects

LEAD Housing Development Programme, Auckland

LEAD Housing Development Programme, Auckland

Drury South Crossing Precinct