Project overview
The Aniwhenua hydroelectric power station is located on the Rangitaiki River in New Zealand’s Bay of Plenty. The headpond embankment is a 100m long, 18.5m high sloping earth core rockfill dam with a low potential impact category.
Following a routine surveillance, Nova Energy identified rehabilitation work was required to keep the headpond operational. To minimise the operational impact of remediation works, Nova Energy required design, consenting and construction of works to be completed within a tight eight-week turnaround time.
Working in partnership with Nova Energy and Waiotahi Contractors, Tonkin + Taylor provided design and construction monitoring services, helping to ensure the complex and challenging project was completed on time and to budget.
Waiotahi Contractors received recognition for their input on the project as the Category 1B winner of the Civil Contractors/Hirepool Construction Excellence Awards 2017. “From the senior management of Waiotahi Contractors and the project team who delivered the completed physical works, thank you Tonkin + Taylor for providing engineering and geotechnical services of such a high quality and in a very timely manner. As the contractor, our performance was a reflection of the efforts of the Tonkin + Taylor team.”